Friday 31 March 2017

'NO MORE FAKE NEWS' says KPC as it issues a press release dubbed 'PURE TRUTH'



In a press statement dubbed as 'No more FAKE news' KPC explains the alleged corruption and inefficiencies that has been raised by corrupt media media outlets and paid blogs. Here is the press release by KPC
KPC-SETTING THE RECORD STRAIGHT

NEW MOMBASA-NAIROBI PIPELINE (Line 5)
Rationale for Line 5
1.    In 2013, KPC carried out a petroleum demand survey for the country with a view to project demands for Kenya and the region up to year 2044 to enable the Company compute the size of replacement for Line 1 between Mombasa and Nairobi. The February 2013 Petroleum Products Demand Projections Report by an independent consultant Shengli Engineering & Consulting Co. Ltd established that the annual petroleum demand  for Kenya in 2013 was 4 billion litres with projected demands of 5.7 billion litres in 2016 and 6.8 billion litres in 2020. This rise in demand was largely due to the country’s economic growth and that of the region.

On the other hand, the demand for the export market of Uganda, Rwanda and eastern Democratic Republic of Congo stood at 2.4 billion litres in 2010 but has since risen to 3.5 billion litres in 2016.
The choice of sizing (20 inch pipeline) was therefore informed by a study carried out by an independent expert consultant (Shengli Engineering & Consulting Co. Ltd) on the projected demand for petroleum products in Kenya and the region served by KPC.
At no time did KPC conceive laying a 16-inch pipeline between Mombasa and Nairobi.
2.    The Current Line 1 (Built in 1978) is 39 years old, and 14 years beyond its design life span.

3.    An in-line inspection carried out by NDT Middle East Co Ltd in 2010 indicated that it was not operationally and economically feasible to carry out repairs to the aging pipeline beyond 2014. This meant that Line 1 had to be replaced.

4.    It was not possible to replace the current line because that would require total shutdown of operations and this would have jeopardised fuel supply in the country and region. Replacement of Line 1 can only be done once line 5 is up and running.


5.    KPC already has parallel pipelines operating simultaneously on its other routes (Nairobi-Eldoret - Line 2 and Line 4; Kisumu-Sinendet,-Line 3 and 6) therefore the decision to build a parallel pipeline was not unusual, but informed by the Company’s operational requirements.  


The Line 5 Procurement Process
The procurement process was carried out in accordance with the provisions of Section 78-82 of the Public Procurement and Disposal Act 2005, between 1st January 2013 when the Expression of Interest (EOI) was first advertised, and 1st July 2014 when the contract was signed between KPC and Zakhem Ltd. This was a period of over one year, and NOT one day as alleged. During that period, the procurement process was investigated and cleared by the Public Procurement Oversight Authority.
The procurement process was unsuccessfully contested by 4 different parties. The courts consistently upheld the award to Zakhem. In particular, China Wu Yi unsuccessfully contested the award to Zakhem and Public Procurement Appeals Review Board (PPARB) directed that  an investigation by the relevant arms of government be carried out on  the conduct of China Wu Yi for tender malpractices.
In her ruling in High Court Petition No 173 of 2014; Rich Productions (K) Ltd –vs- KPC Ltd & PPOA delivered on 19th June 2014, Lady Justice Mumbi Ngugi held that there was no merit in the challenge to the award of the Line 5 tender to Zakhem Ltd as KPC had complied with the provisions of the Public Procurement and Disposal Act, 2005.
Cost of Line 5
The contract sum is Kshs 48 Billion and NOT 53 Billion. The total cost of a new 20-inch, 450-km ultra-modern petroleum products pipeline (‘Line V’) from Mombasa to Nairobi is US$ 484 million, being partially funded with a US$ 350 million (70%) loan. The balance 30% of US$ 134 million of the project cost is being financed from KPC’s own financial resources. The funding was secured because the project is viable and met the ledors threshold requirements for funding.
The US$ 350 million facility  given to KPC by a consortium of banks  comprising CfC Stanbic Bank Limited, Citibank, N.A., [Kenya Branch], Commercial Bank of Africa Limited, Co-operative Bank Limited, FirstRand Bank Limited (London Branch), and Standard Chartered Bank is one of the largest commercial bank financings ever entered into by a Kenyan parastatal on a stand-alone basis and confirms KPC’s solid  financial standing and reputation; and to the ability of Kenyan-based banks to arrange complex financing deals.
The loan carries highly competitive terms: it is for 10 years, and bears a margin of 5.38% over LIBOR, comparable, at present LIBOR rates, to the  financing costs on the recent Kenya Government US$ 2 billion Eurobond issue.
KPC contracted in USD and borrowed funding for the construction and is thus insulated from currency fluctuations. For the record, KPC previously borrowed Kshs 8.2 Billion for the Nairobi – Eldoret (Line 4) capacity enhancement project, which sum was repaid within 2 years after the project was completed, and 5 years earlier than the contracted loan tenure.
Money Paid out to Zakhem International Limited
No money has been lost. As at 28th March 2017, KPC has paid 75.6% of the contract sum amounting to Kshs 34 billion against certified completed work of 82%.
KPC ‘s financiers release the funds directly to the contractor upon receipt of documents certifying work done.
The project is now 82% complete.

The Future of Line 1
In view of the demand for petroleum products in the region which  grows by 8% per annum,   and in line with KPC’s strategy of devolving the pipeline to move the product closer to Wanjiku, KPC shall continue rehabilitating the existing Line 1  and run it as a parallel line as with the other sections of the pipeline network such as Nairobi-Eldoret; and Sinendet-Kisumu.
Capacity Enhancement Pumps
The capacity enhancement project of 2009-2010 that saw new pumps fitted in Samburu (PS 2), Manyani (PS 4), Makindu (PS, 6), and Konza (PS 8), was intended to increase pumping capacity and flow rate for Line 1 from 440m3 per hour to 880m3 per hour, and reduce product stock-outs which had become rampant in the country. This was achieved and the pumps are currently in use and have served the country since 2010.
These pumps will not be discarded but will be synchronised and used as alternatives to the installed pumps on the new pipeline.
Claim for Shs 11 Billion by Zakhem
There is no variation for Shs 11 Billion to the contract between KPC and Zakhem.

Line 5 Expected Benefits
This Vision 2030 project will have the following impact once complete:

1.    Due to the country’s economic growth and expansion of the economy, the current annual demand for petroleum stands at 5.7 billion litres in 2016 up from 4 billion litres in 2013. The new line will therefore adequately serve the country’s demand which is projected to be 6.8 billion litres in 2020. 
2.    The line will enhance KPC’s pipeline devolution plan into the counties by increasing product availability in Nairobi that will feed into spur lines into Western Kenya, Central Kenya, Rift Valley and South Nyanza regions. 
3.    The new pipeline will also enhance and improve the reliability of fuel supply to the export market of Uganda, Rwanda and eastern Democratic Republic of Congo which in 2010 stood at 2.4 billion litres but has since risen to 3.5 billion litres in 2016.
4.    The new line is also expected to improve the safety, reliability and efficient delivery of product to KPC’s customers and reduce the constraint on Ullage on current 14” Mombasa to Nairobi pipeline. 
5.    With a one million litres per hour flow rate, the line will remove an average of about 700 trucks from the road daily at maximum utilization. This will enhance safety because pipeline transportation of fuel is the safest and most cost effective way of transporting petroleum products the world over. There will therefore be no tanker accidents, fuel fires, siphonings on our roads hence saving lives and conserving our environment. 
6.    Reduced pump price – the current price build up compensates truck transporters at the rate of one shilling per litre. Elimination of road transport will save the economy approximately Kshs 4.2 billion per year.  

OTHER LEGACY CONCERNS:
1)    Aero Dispenser Company Limited

Some recent media reports have raised concerns about the current state of Hydrant Pit Valves (HPVs) which were supplied by Aero Dispenser Company. HPVs are instruments that enable the refuelling of aircraft at Jomo Kenyatta International Airport (JKIA), and which are owned and maintained by Kenya Pipeline Company Limited (KPC). Specifically, it has been reported that of the 130 valves installed, 60 have malfunctioned, thereby leading to speculation that JKIA may have to close due to a lack of refuelling capabilities.
Currently, JKIA’s apron has a total of 128 HPVs. Out of these, 122 are operational, while 6 are currently not in service, and need replacement. 

A related and relevant fact is that 43 of the 128 HPVs are earlier generation models. In 2014, KPC decided to replace these with current versions in order to comply with the requirements of the Joint Inspection Group, the global organisation that certifies jet fuel quality. KPC set out to procure 60 HPVs for JKIA, to replace the 43 non-compliant valves with the balance 17 being spares. The HPVs were duly delivered but could not be released for use because the procurement process for the valves became a subject of investigation by the Ethics and Anti-corruption Commission (EACC). These investigations are yet to be concluded. We await EACC’s and the Public Procurement Regulatory Authority’s advice on the way forward.

2)    Sinendet-Kisumu Pipeline (Line 6)
This was a Kshs 5.7 billion 122km 10-inch diameter pipeline parallel to an existing 6-inch diameter pipeline from Sinendet to Kisumu (Line 3) designed to enhance petroleum product availability in the Western Kenya and the export market of Uganda, Eastern DRC, Rwanda, Burundi, and Northern Tanzania.

During the procurement process, Petroject failed to comply with the tender requirements on provision of a Performance Bond resulting in cancellation of the tender.
The subsequent contractor (China Petroleum Pipeline Bureau) was selected following a new open tender, and he delivered the project on time and within budget. The project was commissioned in May 2016 and currently serves the Western Kenya regional market, which previously suffered frequent product shortages.
3)    Eldoret Truck Bottom Loading

The upgrade of Eldoret Depot (PS27) loading facilities was necessitated by the increased West Kenya Pipeline Extension (WKPE) capacity from 220 cubic meters per hour to the current combined capacity of 578 cubic meters per hour. The number of trucks that queue to pick products from west Kenya depots has risen over time and this has led to congestion within the depots. KPC has lost business as a result of dealers preferring the Southern corridor (Tanzania) that does not experience the level of delays that are common in KPC West Kenya depots.
The main objective of the project is therefore to enhance the existing facilities to meet the anticipated increase in product uplifts by up to 2000 cubic meters per day. 
The initial EMPRO contract lapsed in 2015, and a new tender for the remaining works was issued in accordance with the provisions of the Public Procurement and Asset Disposal Act 2015.
Currently, the project is 92% complete is expected to be completed in April 2017.

Conclusion
KPC assures the nation that the Company remains committed to deliver on its mandate.  The company is open and willing to avail all necessary information required.
KPC would like to inform its stakeholders and Kenyans at large that it remains focused on delivery of its mandate by ensuring safe, efficient delivery of petroleum products from source to customer not only in Kenya but within the region.


JOE SANG

MANAGING DIRECTOR